What does he mean with reworks? Changing an defect engine before delivery?
|
|
philidor
in service - 6 years
Posts: 8,950
|
Post by philidor on Aug 25, 2013 17:24:11 GMT 1
What does he mean with reworks? Changing an defect engine before delivery? All 787s up to LN 65 had to undergo extensive rework before delivery. The earlier frames required many months of rework. The EMC (Everett modification center), which performs that work, is scheduled to be closed no sooner than 2015.
|
|
|
Post by peter on Aug 26, 2013 2:06:37 GMT 1
The first 787's (line no 7 through 19) needed around 6000 modifications. Line no 66 needed only about 300.
|
|
seibedom
Final Assembly Line stage 1
Posts: 251
|
Post by seibedom on Aug 26, 2013 5:19:30 GMT 1
Wow, didn't know they still need that many!
|
|