Post by addasih on Jul 18, 2016 20:28:06 GMT 1
It is very weird that we still don't know the frame carried even though it arrived in TLS few days ago
|
|
|
Post by addasih on Jul 18, 2016 23:46:32 GMT 1
|
|
|
Post by FabienA380 on Jul 19, 2016 7:38:06 GMT 1
That's interesting, the 2 missing pieces should be one wing and the Rear Fuselage?........
|
|
s543
in service - 2 years
Posts: 3,957
|
Post by s543 on Jul 19, 2016 8:36:12 GMT 1
Fabien how any times was it before that next convoi carried the the leftovers. It must be much more expensive and than why just not wait few days. They do not need the parts so fast anyway ?
|
|
|
Post by FabienA380 on Jul 19, 2016 8:54:27 GMT 1
Countless times in fact, every time there was not a full frame convoyed.....
|
|
philidor
in service - 6 years
Posts: 8,950
|
Post by philidor on Jul 19, 2016 10:08:24 GMT 1
I suspect these convoy issues must be a consequence of the ongoing production rate change.
|
|
s543
in service - 2 years
Posts: 3,957
|
Post by s543 on Jul 19, 2016 10:15:59 GMT 1
1. Did not happen in last few years ! 2. If you would want to slow down why just not omit a whole convoi ?
The reason might be that the some parts from next convoi were not yet ready for transport ?
|
|
philidor
in service - 6 years
Posts: 8,950
|
Post by philidor on Jul 19, 2016 15:17:23 GMT 1
I think a rate change creates disruptions for all suppliers, but there may be marked differences between them. Airbus must be juggling with constraints, and what we see is a transition to the new rate.
EDIT : I notice I now have got three red stars, which I think is one more than I used to have. Is it because I passed the 4500 post milestone ?
|
|
mjoelnir
in service - 2 years
Posts: 4,089
|
Post by mjoelnir on Jul 19, 2016 16:09:30 GMT 1
I think a rate change creates disruptions for all suppliers, but there may be marked differences between them. Airbus must be juggling with constraints, and what we see is a transition to the new rate. EDIT : I notice I now have got three red stars, which I think is one more than I used to have. Is it because I passed the 4500 post milestone ? Up to now it does not look much like a build rate change. The convoy bringing the rest after 16/2016 seems to be an add on convoy, leading to two convoys in August.
|
|
|
Post by FabienA380 on Jul 19, 2016 21:10:17 GMT 1
|
|