Post by s543 on Jun 23, 2015 12:45:51 GMT 1
It is nice - we should have 2 deliveries/month for 3 month at least
|
|
|
Post by stealthmanbob on Jun 23, 2015 14:57:51 GMT 1
I try to summarize the status of the MSN<=20 in the order acc planned delivery: VN1 MSN14 DC, del. Jun QR5 MSN8 painted engine attach, del. Jul VN2 MSN15 painted engine attach, del. Jul QR6 MSN11 painted engine attach, del. Aug VN3 MSN16 painted engine attach, del. Aug AY1 MSN18 painted engine attach, del. Sep unclear, does anyone know the paint status? VN4 MSN17 QR7 MSN12 QR8 MSN13 AY2 MSN19 AY3 MSN 20 According to the site below, which is quite good, your paint status question is answered, all 5 still un painted ? sites.google.com/site/a350xwbproduction/production-list
|
|
sciing
in service - 1 year
Enter your message here...
Posts: 2,503
|
Post by sciing on Jun 24, 2015 19:02:34 GMT 1
I guess philipp use this site and especially XWB insider infos as source
|
|
sciing
in service - 1 year
Enter your message here...
Posts: 2,503
|
Post by sciing on Jun 24, 2015 19:08:06 GMT 1
Thanks sciing that's a very nice summary!! (I've moved it here if it's okay) My idea was to make an FAL status summary like XWB has done so great several times. The delivery dates I had just read on A.net in a post by the well known Richard. I guess philipp has an even better overview on his site. But I will create a new with the status of MSN13, 17, 12 from lateast XWB infos
|
|
XWB
in service - 11 years
Posts: 16,115
|
Post by XWB on Aug 19, 2015 10:53:56 GMT 1
|
|
|
Post by stealthmanbob on Aug 19, 2015 11:07:52 GMT 1
|
|
|
Post by addasih on Sept 4, 2015 13:22:24 GMT 1
No deliveries in August
|
|
XWB
in service - 11 years
Posts: 16,115
|
Post by XWB on Sept 4, 2015 13:35:11 GMT 1
Current delivery schedule:
September - MSN 8 QR - MSN 15 VN
October - MSN 11 QR - MSN 16 VN - MSN 18 AY
November - MSN 13 QR - MSN 17 VN - MSN 19 AY
December - MSN 12 QR - MSN 20 AY - MSN 24 JJ
This will mark the 15 deliveries for 2015.
If everything goes well MSN 21 and 22 may be delivered too.
|
|
ghorn
Outfitting in Hamburg
Posts: 993
|
Post by ghorn on Sept 16, 2015 23:56:07 GMT 1
All of these are now painted except 12 and 21 which are both for QR. Hopefully they will still be delivered in 2015 to make a total of 17. Geoff Current delivery schedule: September- MSN 8 QR - MSN 15 VN October- MSN 11 QR - MSN 16 VN - MSN 18 AY November- MSN 13 QR - MSN 17 VN - MSN 19 AY December- MSN 12 QR - MSN 20 AY - MSN 24 JJ This will mark the 15 deliveries for 2015. If everything goes well MSN 21 and 22 may be delivered too.
|
|
mjoelnir
in service - 2 years
Posts: 4,089
|
Post by mjoelnir on Sept 17, 2015 11:34:08 GMT 1
The status of MSN12 is strange, she is said to be in engine attachment and unpainted in sites.google.com/site/a350xwbproduction/production-listIf she is in 20 for engine attachment she should be painted. MSN21 is in the paint shop and MSN22 is in 20 for engine attachment. Both should be far enough in the process for being delivered this year.
|
|