Updated database [ Reply # 54 on Page 6 or click .] of the 787 Dreamliner aircraft with the last three delivered Boeing 787-9s: Published on 30. Jun 2016 British Airway's Boeing 787-9 Dreamliner, reg. G-ZBKL performs a missed approach on a customer test flight: Mario
|
|
|
Post by stealthmanbob on Jul 28, 2016 11:04:13 GMT 1
Post #2 updated, 10 deliveries so far in July, 3 or 4 more expected !
|
|
|
Post by stealthmanbob on Aug 1, 2016 16:10:30 GMT 1
Post number 2 updated with the July deliveries, 14 again
|
|
|
Post by stealthmanbob on Aug 4, 2016 17:29:06 GMT 1
First August Delivery now on post #2, August will probably be a relatively quiet month, only 8-9 deliveries expected
|
|
|
Post by stealthmanbob on Aug 9, 2016 13:22:49 GMT 1
A rather odd development for the B787 !
"Near term deliveries of the 787 look to slow down due to unspecified issues with the thrust reversers affecting both GE and Rolls Royce powered aircraft. A source has indicated that this is not a fleet wide problem but concerns a batch of thrust reversers that are installed on current 787s that are on the flightline or that are currently being assembled. New thrust reversers without the issue have been manufactured and are being installed on several aircraft on the flightline including ones for Hainan, JAL and Scoot as those aircraft have their engines removed"
From - nyc787.blogspot.co.uk
|
|
|
Post by stealthmanbob on Aug 17, 2016 11:41:46 GMT 1
Post number 2 updated with 2 more deliveries, it is going to be a very low number this month !
|
|
mfranjic
Final Assembly Line stage 1
Posts: 222
|
Post by mfranjic on Aug 27, 2016 23:13:38 GMT 1
The database [ Reply #54 on Page 6 or click .] of the 787 Dreamliner aircraft was updated with the latest delivered aircraft, and the last of them, 89th in 2016 and 452nd overall, is Air China´s 5th Boeing 787-9 Dreamliner - MSN 34309 / LN 462, reg. B-7832 (test reg. N8291V), produced in Charleston, with the cabin configuration C30 W34 Y229 and powered by twin Trent 1000-K2 three-shaft turbofans (fan diameter: 2.845 mm / 112 in; eng. architecture: F-8IPC-6HPC ^ 1HPT-1IPT-6LPT), each 347,54 kN / 35.439 kgf / 78.129 lbf, delivered on 27. Aug 2016, flying on the route CHS - PEK.
B-7832 on its way home...
.
Mario
|
|
|
Post by stealthmanbob on Sept 1, 2016 11:42:33 GMT 1
Post #2 updated with 4 more August deliveries, I will update the totals in a day or so.
|
|
|
Post by stealthmanbob on Sept 2, 2016 10:56:05 GMT 1
Post #2 updated, 10 deliveries in August, 92 YTD.
|
|
|
Post by stealthmanbob on Sept 7, 2016 13:34:02 GMT 1
Post #2 updated with the first delivery for September. I am expecting 12 deliveries this month, which may include 2 troubled teens LN 13 and LN 15 ?
|
|